The first method is generally preferable for single-span bridges, as it is possible to keep the beam raised using road-rail loaders. Transversal unrolling is instead preferable for multi-span bridges, which require the laying of a sequence of several membranes.
Once the first membrane has been laid, a metal edge is placed on it which will act as a paraballast element during the laying of the next membrane. The vertical edge of the membrane is temporarily fixed to the outside of the side.
Once the ballast has been rebuilt on the first membrane and the excavation for the installation of the second membrane has been completed, the vertical edge of the first membrane is freed from the bank and is placed horizontally at the base of the same.
After the installation of the second membrane, the junction between this and the first is made, using a riveted joint, which must be along a watershed line.
Once the joint has been completed, the temporary bank is removed and the railway ballast is reconstructed on membrane 2.